GQC: TSX-V

The ROMERO PROJECT PFS Highlights

  • Maiden Probable Mineral Reserves of 7.03 million tonnes containing:
    • 840,000 ounces of gold
    • 980,000 ounces of silver
    • 136 million pounds of copper
  • A 2,800 tonnes per day operation totalling life of mine gold equivalent production of approximately 1.117 Moz AuEq
  • Annual gold equivalent production averaging 109,000 ounces per year
  • Post tax Net Present Value @ (5%) of $203 million (pre tax $317 million)
  • All-in Sustaining Cost of $595/oz AuEq
  • Post tax Internal Rate of Return of 28% (pre-tax 38.6%)
  • Initial Capex of $158.6 (Life of Mine $250.9 including sustaining and closure)
  • Life-of-mine ("LOM") all-in sustaining costs ("AISC") of $595/oz gold equivalent ("AuEq") payable.
  • Payback of capital within 2.5 production years.
  • Pre-production capital expenditure estimate of $158.6 million, plus $92 million of sustaining and closure capital over LOM totaling $250.9 million.
  • An eight-year underground mine at an average production rate of 1,022,000 tonnes per year (2,800 tonnes per day) with an average production of 109,000 recovered AuEq oz per year.
  • Total metal recoveries consisting of 78.1% for gold, 58.6% for silver 94.6% for copper to a single concentrate for sale to copper smelters. There are no perceived penalty elements.
  • The PFS contemplates an environmentally proactive approach. Some of these features include:
    • A small surface footprint over the underground mine
    • The use of cyanide is not included in the design. A flotation concentrate product will be shipped from the Puerto Viejo port to international smelters; 
    • 100% of the waste rock from the underground mine will be returned underground as backfill to eliminate the potential for acid rock drainage;
    • The project is designed to capture run-off water to supply the mine, thus avoiding any water taking from the San Juan river;
    • Tailings from the process plant will be filtered, dried and placed in a dry stack storage facility.  No tailings ponds or dam structures will be required;
    • Power will be supplied by a line connection to the domestic power grid;
    • Ventilation fans will be located underground to reduce noise; and
    • No relocation of the Hondo Valle village, or any settlements.

JDS Energy & Mining Inc. is a Vancouver based mining consulting company, who has extensive experience in mining and development studies.  JDS assembled a multi-disciplinary international team of experts to conduct the Romero PFS including:

  • Micon International Limited (Micon) (geology, mineral resources)
  • Golder Associates Limited (geotechnical, tailings and water management)
  • Allnorth Consultants Limited (process design)
  • MineFill Services Incorporated (backfill plant design)

GoldQuest applied for a mining permit to the Dominican Ministry of Energy and Mining in November 2015 and has commenced baseline studies for the environmental permitting process. 

Romero Photos

access road
access road
field camp
field camp
geologist looking sw across escandalosa zone
geologist looking sw across escandalosa zone
romero project and base camp in hondo valle
romero project and base camp in hondo valle